WGA developed a new 30m3 bulk gypsum hopper, belt feeder and support structure to replace the ageing and heavily corroded existing equipment. Limited shutdown time dictated that the new concrete footings and steel structure had to be constructed external to the existing building while the plant continued to operate. Point cloud scanning of the existing equipment, conducted in-house, was utilised to manage interfaces with key retained equipment.