The Project
WGA provided full Engineering, Procurement and Construction Management (EPCM) delivery of several raise bore ventilation fans with a total value exceeding $150m.
Services included cost estimation and early planning to support funding applications.
Technical Solutions
WGA facilitated HAZID workshops, undertook detailed engineering design across all disciplines and provided full-time site construction management, including cost and schedule control.
Client Focus
WGA reduced construction time for each installation by more than 2 months and reduced costs by more than 15% while maintaining an impeccable safety record.
The Raise Bore Fan EPCM is included in the following sectors & services.
Click on one to find out more about that sector or service.